Official DPRTE 2022 event partner, the Defence Infrastructure Organisation (DIO), has completed a significant series of upgrades to the Northern Ammunition Jetty at Glen Mallan near Helensburgh.

The jetty, which is used to load and unload ammunition for the Royal Navy’s surface fleet, was last upgraded in the 1970s and had reached the end of its economic life. The upgrade work has not only extended the life of the jetty by an estimated fifty years, but has also made the site accessible for the Royal Navy’s aircraft carriers, HMS Queen Elizabeth and HMS Prince of Wales.

The £67-million pounds contract was awarded to VolkerStevin in 2019. Alongside them, DIO also worked with managing agent Jacobs, who provided engineering and professional services, as well as designer Arch Henderson.

In completing this major project, £20-million pounds was spent with local suppliers and small and medium enterprises in Scotland.

The previous jetty was demolished and replaced with a new 135m long jetty structure, requiring 127 steel piles to be driven into the loch bed to support a reinforced concrete deck. The works also included the installation of navigation aids and five mooring dolphins which are connected to the jetty by a pedestrian access bridge.

Two modular fender spacer units have been placed in front of the new fender panels and move with the tide to prevent the overhanging flight decks of HMS Queen Elizabeth and HMS Prince of Wales from colliding with the jetty.

In addition, the project included the installation of two modern pedestal cranes to load and unload ammunition and the erection of modular buildings for offices, power generation and stores. The perimeter fencing and CCTV system have also been upgraded to provide a complete modern facility.

The team faced a challenge when the scale of HMS Queen Elizabeth’s first planned deployment increased, resulting in the need for the jetty to be operational nine months earlier than originally planned. All parties worked closely together to progress the project sufficiently for the Royal Navy’s flagship to be able to berth at the unfinished jetty, which she did successfully in March this year.

Sustainability and protecting the environment of Loch Long was an important consideration for the project team. The use of capture blankets prevented material from entering the water when the old jetty was demolished. All jetty demolition waste was transported on barges offsite to recycling facilities on the Clyde to minimise disruption to the public and will be reused for construction. To avoid the need to lay new electric cables through the water, the new navigation aids are solar powered.

There were concerns about the possible impact of noisy piling works on marine mammals, so two observers used underwater listening devices, along with visual inspections, to make sure no marine mammals were in the area before work began. If any were located, work was stopped to give them time to move away.

Craig MacDonald, DIO’s Project Manager, said: “It’s been such a pleasure to work on such a nationally-important and dynamic project. The project has faced numerous challenges, but they have been overcome with good teamwork, communication and collaboration. It’s great to see this vitally important facility now in full operation.”

John Cox, Managing Director, VolkerStevin said: “We are very proud to have played a key role in the successful delivery of all three phases of the Queen Elizabeth Class Aircraft Carrier infrastructure upgrade programme. The completion of this final phase, is testament to the hard work and commitment of the entire team, and demonstrates the benefits of a strong collaborative approach in the delivery of complex critical infrastructure projects.”

Justin Goldberg, Jacobs’ Vice President for Defence & Security, said: “As Principal Service Provider, we managed the contract on behalf of DIO as part of a dedicated team with the vision and drive to keep this project moving forward. Through early contractor engagement and close collaborative working, we were able to deliver within budget and programme constraints, providing the Royal Navy with an important facility for years to come while ensuring sustainability and protection of the environment. We are now applying best practice from this exemplar project to other maritime work.”

As a critical national infrastructure project, work continued through the pandemic with all necessary precautions taken and guidance followed to keep everyone safe.

The jetty was handed over to Defence Equipment and Support, who will operate it. The Glen Mallan Northern Ammunition Jetty is the third and final jetty refurbishment to support the nationally critical £7-billion Queen Elizabeth Class (QEC) Aircraft Carrier programme.

image © VolkerStevin 2021

DIO is an official DPRTE 2022 event partner

Taking place at Farnborough International on May 5th, DPRTE 2022 is the UK’s leading defence procurement and supply chain event.

For all involved within buying for or supplying to the defence sector, it’s an unmissable opportunity to hear from and engage with industry leaders, influencers and stakeholders.

To register today as a delegate, follow this link.

To take advantage of exhibitor or sponsor opportunities, please click here.

Defence Online is the official media partner for DPRTE 2022

If you would like to join our community and read more articles like this then please click here

Defence Infrastructure Organisation DIO DPRTE Glen Mallan Royal Navy VolkerStevin

Post written by: Matt Brown

LATEST STAKEHOLDER

Become a Stakeholder today and benefit from an exclusive marketing package which will allow you to:

  • Engage with active defence buyers and key supply chain partners
  • Create your own branded micro-site which within Defence Online which is managed by you
  • Have a dedicated Digital Account Manager to help enhance your Stakeholder page
  • Promote your news, products, press releases, eBooks and Videos as a Defence Online partner which feeds through to our homepage and social media channels
  • Have your company promoted on our partner website Defence Contracts Online (DCO)
  • All news promoted in mynewsdesk, a major hub for all of our news articles which enables news to be picked up from trade magazines, national newspapers and many other publications which offers extra exposure at no additional cost!

Contact us today or call us on 0845 557 1315 to take advantage of this exclusive marketing package


RELATED ARTICLES

Royal Navy have concluded a contract-signing and groundbreaking ceremony for a major construction project at Royal Naval Air Station (RNAS) Culdrose in Cornwall. 

November 21, 2024

Homeland - DIO and Royal Navy sign contract for construction project in Cornwall

The Defence Infrastructure Organisation (DIO) and the Royal Navy have concluded a contract-signing and groundbreaking ceremony for a major construction

DPRTE partner DIO awards £1.6bn contracts to upgrade UK Defence estate

November 18, 2024

Homeland - MOD signs advisors to develop surplus land for community use

Local communities will benefit from real estate and environmental & technical advice in developing surplus Defence sites for residential use. The